Owner / Applicant Information
Steve R Rice
Rice Real Estate LLC
14450 GETZ RD.
NOBLEVILLE IN 46060
Phone 3175023618
Email [email protected]
Submitter Information
Jackie   Lynn
Mooring USA
7802 SW 820
Benbrook IN  
Phone 8176885616
Email [email protected]
Designer Information
Mike   Stenstrom 
Stemstrom Schneider Inc
13748 Neutron Rd
Dallas TX  
Phone 2144619831
Email [email protected]
Project Information
Caliber Collision Carmel Fire Restoration
503 W CarmelDr
Carmel TX 46033
County HAMILTON
Project Type New   Addition   Alteration   Existing Y Change of Occupancy  
Project Status F F=Filed U or Null=Unfiled
IDHS Issued Correction order? yes No
Violation Issued by: NA
Local Building Official
Phone: 3175712470 Email: [email protected]
Local Fire Official 
3175712470 Email: [email protected]
Phone:

Variance Details
Code Name:  Other Code (Not in the list provided)
675 IAC 12-6-3(a) 12-6-7(g) 13
Conditions: We are requesting a variant for the fire suppression system condition per the construction  design release.  We are restoring the building the back to its preexisting condition prior to  the loss.  Previously, there wasn't a suppression system for the existing building.  We are  not adding any new square footage, nor changing the floor plan in any way. The existing  exterior wall and windows are still in place and were not damaged during this loss.  
However, there was a fire suppression for the paint booth prior to the loss. That will be  submitted to the Indiana DHS office by the paint booth company. They have file and received  their own CDR from the state. 
We appreciate your consideration regarding this variant request
DEMONSTRATION THAT PUBLIC HEALTH, SAFETY, AND WELFARE ARE PROTECTED:
1=Non-compliance with the rule will not be adverse to the public health, safety or w
1
2= Applicant will undertake alternative actions in lieu of compliance with the rule to  ensure that granting of the variance will not be adverse to public health, safety, or  welfare.  Explain why alternative actions would be adequate (be specific).
Facts:  
DEMONSTRATION OF UNDUE HARDSHIP OR HISTORICALLY SIGNIFICANT STRUCTURE:
Imposition of the rule would result in an undue hardship (unusual difficulty)  because of physical limitations of the construction site or its utility services.
Y
  Imposition of the rule would result in an undue hardship (unusual difficulty)  because of major operational problems in the use of the building or structure.
Y Imposition of the rule would result in an undue hardship (unusual difficulty)  because of excessive costs of additional or altered construction elements.
  Imposition of the rule would prevent the preservation of an  architecturally or a historically significant part of the building or structure
Facts:  

Variance Details
Code Name:  Other Code (Not in the list provided)
675 IAC 12-6-3(a) 12-6-7(g) 13
Conditions: We are requesting a variant for the fire suppression system condition per the construction  design release.  We are restoring the building the back to its preexisting condition prior to  the loss.  Previously, there wasn't a suppression system for the existing building.  We are  not adding any new square footage, nor changing the floor plan in any way. The existing  exterior wall and windows are still in place and were not damaged during this loss.  
However, there was a fire suppression for the paint booth prior to the loss. That will be  submitted to the Indiana DHS office by the paint booth company. They have file and received  their own CDR from the state. 
We appreciate your consideration regarding this variant request
DEMONSTRATION THAT PUBLIC HEALTH, SAFETY, AND WELFARE ARE PROTECTED:
1=Non-compliance with the rule will not be adverse to the public health, safety or w
1
2= Applicant will undertake alternative actions in lieu of compliance with the rule to  ensure that granting of the variance will not be adverse to public health, safety, or  welfare.  Explain why alternative actions would be adequate (be specific).
Facts:  
DEMONSTRATION OF UNDUE HARDSHIP OR HISTORICALLY SIGNIFICANT STRUCTURE:
Imposition of the rule would result in an undue hardship (unusual difficulty)  because of physical limitations of the construction site or its utility services.
Y
Imposition of the rule would result in an undue hardship (unusual difficulty)  because of major operational problems in the use of the building or structure.
 
Y Imposition of the rule would result in an undue hardship (unusual difficulty)  because of excessive costs of additional or altered construction elements.
  Imposition of the rule would prevent the preservation of an  architecturally or a historically significant part of the building or structure
Facts: