Variance Details |
|
|
|
|
Code Name: |
|
Other Code (Not in the list provided) |
|
|
|
|
|
|
2014 IFC 903.2.6 |
|
|
|
|
|
Conditions: |
|
Piece by Piece ABA Therapy Center is a company that provides one on one therapy for children that are on the spectrum for Autism. They moved into this building earlier in the year unknowing that a fire sprinkler system was required for their operation. This was discovered upon inspection by the local fire department.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
DEMONSTRATION THAT PUBLIC HEALTH, SAFETY, AND WELFARE ARE PROTECTED: |
|
|
|
|
|
1=Non-compliance with the rule will not be adverse to the public health, safety or w |
|
|
|
|
1 |
|
|
|
2= Applicant will undertake alternative actions in lieu of compliance with the rule to ensure that granting of the variance will not be adverse to public health, safety, or welfare. Explain why alternative actions would be adequate (be specific).
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Facts: |
|
Each client is served by one employee. The building is equipped with a monitored fire alarm and there are 4 exits installed in the building when there are only 2 exits required.
|
|
|
|
|
|
|
|
|
DEMONSTRATION OF UNDUE HARDSHIP OR HISTORICALLY SIGNIFICANT STRUCTURE: |
|
|
|
|
|
|
Imposition of the rule would result in an undue hardship (unusual difficulty) because of physical limitations of the construction site or its utility services.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Imposition of the rule would result in an undue hardship (unusual difficulty) because of major operational problems in the use of the building or structure.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Y |
|
Imposition of the rule would result in an undue hardship (unusual difficulty) because of excessive costs of additional or altered construction elements.
|
|
|
|
|
|
|
|
|
|
|
|
Imposition of the rule would prevent the preservation of an architecturally or a historically significant part of the building or structure
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Facts: |
|
This building is a single story wood framed building built over a full basement at approximately 6,250 square feet per floor. Currently the basement is fully sprinklered but not the first floor or attic. Brown Sprinkler estimated installing sprinklers on the first floor and attic would be approximately $63,125.00. Piece by Piece is currently leasing the space but is in negotiations for purchasing the property. They can't afford to install the sprinkler system at this time and are asking to delay the installation of the sprinkler system until December 31, 2020 when their lease is up and hopefully they purchase the building.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|