Owner / Applicant Information
Douglas K Marsh
University of Notre Dame
200 FACILITIES BUILDING
NOTRE DAME IN 46556
Phone 5746317900
Email [email protected]
Submitter Information
Edwin L Rensink
RTM Consultants Inc
6640 Parkdale Place
Indianaplis IN  
Phone 3173297700
Email [email protected]
Project Information
US Senior Open Tent Structures
110 Warren Golf Course Clubhouse
Notre Dame IN 46556
County ST JOSEPH
Project Type New Y Addition   Alteration   Existing   Change of Occupancy  
Project Status U F=Filed U or Null=Unfiled
IDHS Issued Correction order? No No
Violation Issued by: NA
Local Building Official
Phone: 5742359554 Email: [email protected]
Local Fire Official 
Phone: 5742359554 Email: [email protected]

Variance Details
Code Name:  Other Code (Not in the list provided)
3103.5, 2014 IFC
Conditions: Temporary tent structures are being erected on the Warren Golf Course at the University of  Notre Dame for use during the US Senior Open from June 22-30.  The tents will be erected for a period exceeding 30 days, which is the limit per IFC Indiana amendment.  Tents are being  erected and outfitted from the middle of April until the beginning of the event.  
The temporary tents will be used for hospitality, catering, and dining.  
DEMONSTRATION THAT PUBLIC HEALTH, SAFETY, AND WELFARE ARE PROTECTED:
1=Non-compliance with the rule will not be adverse to the public health, safety or w
1
2= Applicant will undertake alternative actions in lieu of compliance with the rule to  ensure that granting of the variance will not be adverse to public health, safety, or  welfare.  Explain why alternative actions would be adequate (be specific).
Facts: 1. The tents will be erected for a period significantly less than 180 days - the limit for  temporary tent structures in the un-amended IFC.
2. The tents will be occupied by the public for only a week.
3. All tents comply with the NFPA 701 flame propagation criteria.
4. All tents otherwise comply with all requirements of Sec. 3013 and all applicable
requirements of Sec. 3104.
DEMONSTRATION OF UNDUE HARDSHIP OR HISTORICALLY SIGNIFICANT STRUCTURE:
Imposition of the rule would result in an undue hardship (unusual difficulty)  because of physical limitations of the construction site or its utility services.
 
Imposition of the rule would result in an undue hardship (unusual difficulty)  because of major operational problems in the use of the building or structure.
Y
  Imposition of the rule would result in an undue hardship (unusual difficulty)  because of excessive costs of additional or altered construction elements.
Imposition of the rule would prevent the preservation of an  architecturally or a historically significant part of the building or structure
 
Facts: The tent structures will be occupied by the public for just a week.  The additional time is  needed for erection and outfitting of the tents, which cannot be logistically completed within  the 30-day time frame.